OpenShift 4 Cluster AWS

Completed30. December 2020 at 9:0 – 28. January 2021 at 18:30UTC
  • Update28. January 2021 at 18:30UTC

    Maintenance has completed successfully.

  • Update4. January 2021 at 6:43UTC

    The infrastructure nodes have been fixed, all components and services are now up and running.

  • Completed30. December 2020 at 15:19UTC

    Upgrade of cluster was completed successfully but infra nodes are not in a healthy state. Case with Red Hat has been opened.

  • In progress30. December 2020 at 9:8UTC

    Maintenance is now in progress.

  • Planned30. December 2020 at 9:0UTC

    We are updating the OpenShift cluster on AWS from 4.5 to 4.6. The availability of the API and control plane will be degraded during the update. Applications running on the cluster will be redeployed automatically during the final stage of the update.